This page will be utilized as a forum to ensure all interested parties remain up-to-date on the status of the SEMO Day1+ Project. Links will be maintained to key documents to support Market Participants and other parties, including:
- SEMO Day 1+ Project Scope as of the end of March 2008
- Central Market Systems User Requirement Specifications
- Interface Specifications/MPUD Documentation- Key Project Milestones
- Other documentation necessary to support Day 1+ implementation by the agreed date
Should there be any changes to the scope of the Day1+ Project, these changes will be referenced on this page including any consequential impacts on the overall project schedule should they occur.
Following consultation with the Market Participants, TSOs and other interested parties over the period January-March 2008, SEMO submitted its proposal to the Regulatory Authorities (RAs) on 14th March 2008 regarding the proposed scope, timeframe and costs of its Market System Development Plan (MSDP) which it intended to deliver through its Day1+ Project. Following consideration by the RAs SEM Committee and following receipt of clarifications from SEMO, the RAs on 4th April 2008 approved the scope of SEMO’s Day1+ Project as follows:
Logical Group ID / Modification ID | Logical Group / Modification Description |
LG014 | Validation of Registration and Technical Offer Data |
LG016 | Validation of SO/IA Data Transactions |
LG015 | Validation of MI to Settlements Interface |
LG013 | Validation of Data for Operational Scheduling |
LG008 | Screen Based Query of Registration Data |
LG001 | Ex-Post Loss Of Load Probability Forecast |
LG012 | Unique Identification of Data Transactions |
LG011 | Maximum Value for Settlement Reallocation Agreements |
LG017 | Inclusion of VAT Number on Settlement Invoices |
LG002 | Publication of the Required Credit Cover Report |
LG010 | SEMO Branding |
Mod_86 | Publication of Shadow Prices |
Mod_87 | Publication of Aggregated Loss Adjusted Net Demand |
Mod_20 | Publication of Commercially Sensitive Data – Supplier Volumes |
The table below identifies the key milestones throughout the SEMO Day1+ Project in order to deliver on the scope of change identified above.
Completion Date | Milestone / Description |
4th April 2008 | Regulatory Authority Approvals Received by SEMO |
4th April 2008 | Project commencement by Prime Contractor |
7th April 2008 | Baseline of Central Market Systems (CMS)User Requirements Specifications (URSs) |
18th April 2008 | Finalisation of Contractual Arrangements with Prime Contractor |
12th May 2008 | First Draft of MPUD / GPUD issued |
11th June 2008 | Baseline of all Market Participant and TSO Interface Schema |
11th June 2008 | Market Participant Interface User Guide |
13th June 2008 | Baseline of MPUD / GPUD issued |
29th August 2008 | Completion of Prime Contractor’s Development and Test Activities in Factory |
10th October 2008 | Completion of Site Acceptance Test Activity in SEMO |
28th November 2008 | Completion of SEMO System Integration and Regression Test Activities |
1st December 2008 | Commencement of Market Participant Test Activity with SEMO |
12th December 2008 | Completion of Market Participant Test Activity with SEMO |
16th January 2009 | CMS Software Released onto Production Environment |
16th January 2009 | Day1+ Project Completed |
SEMO anticipates that it will have completed all essential Day1+ Project activities including Market Test by 12th December 2008. However, in reviewing SEMO project submission, the SEM Committee highlighted the significant risks associated with deployment of major changes to the Central Market Systems just prior to the Christmas holiday period, in that should unforeseen errors materialise shortly thereafter, there could be a shortage of skilled resources to resolve these over the holiday period. As such, in order to mitigate these risks, SEMO intends to defer the physical deployment of these changes until a later agreed date in January 2009. SEMO currently considers 16th January 2009 as being an appropriate date for this software release to occur but requires acceptance by Market Participants, TSOs and IA of this proposed timeframe.
The proposed scope of the SEMO Day1+ Project is likely to have, in the opinion of SEMO, varying degrees of impact on Market Participants, TSOs and IA. As part of the consultation process, SEMO requested all Market Participants, the TSOs and the IA to provide an indication of the likely cost to their organisation to implement each of the proposed groups of logical changes in the Consultation. Based on the responses received and on the RAs determination of project scope, SEMO has assumed that the likely impact will be as follows, although all potentially impacted parties are advised to perform their own individual assessments. Based on the responses provided by the various organisations, those proposed changes within the approved scope which are likely to have an impact on Market Participants are as follows:
-LG017 – Inclusion of VAT Number on Settlement Invoices;
-LG002 – Publication of the Required Credit Cover Report;
-LG011 – Maximum Value for Settlement Reallocation Agreements;
-LG001 – Ex-Post Loss Of Load Probability Forecast;
-Mod_86 – Publication of Shadow Prices;
-Mod_87 – Publication of aggregated loss adjusted net demand; and
-Mod_20 – Publication of Commercially Sensitive Data – Supplier Volumes (This approved Modification had been bundled with LG005 in previous documentation).
Based on the response provided by the two TSOs, those proposed changes within the approved scope which are likely to have an impact on the TSOs / IA are as follows:
-LG001 – Ex-Post Loss Of Load Probability Forecast;
-LG012 – Unique Identification of Data Transactions;
-LG013 – Validation of Data for Operational Scheduling; and
-LG016 – Validation of SO/IA Data Transactions.
A number of other proposed changes within the approved scope are considered by SEMO to primarily only have an impact on SEMO systems and processes and therefore have no direct impact on other organisations. These are as follows:
-LG010 – SEMO Branding;
-LG008 – Screen Based Query of Registration Data;
-LG014 – Validation of Registration and Technical Offer Data (LG014 is likely to impact on TSOs Business Process ); and
-LG015 – Validation of MI to Settlements Interface.
SEMO MSDP Approved Scope, Key Milestones and Project Management Overview
SEMO is a joint venture between EirGrid plc and SONI Limited